Mooring Systems Flexible Flowline for BP Valhall Project

Moorings Systems has completed the installation of a flexible export flowline to transfer water to a DP tanker at the BP Valhall platform complex in the Norwegian North Sea. The project involved installation of 1,160 metres, 6” flexible flowline, front end engineering, mobilisation of equipment, and offshore installation team.

Located in 70 m of water, the Valhall complex consists of five separate, bridge-connected, steel platforms for quarters, drilling, wellheads, production and water injection respectively. In addition the field has two unmanned flank platforms, one in the south and one in the north, both around 6 kilometers from the field centre.

From its Montrose quayside facility, Mooring Systems deployed a 150t spooler containing five sections of Manuli hose (3 x 300m, 120m and 140m) on the DP vessel Olympic Zeus. The flowline was connected to the production platform using a specially designed ‘hang off spool’ fitted to the end of the hose and the 1,160 m hose laid along the sea bed away from the platform.

A 20” Pusnes connector was fitted to the end of the hose, and laid on the sea bed complete with pick up rope and marker buoys, for subsequent retrieval by DP tanker. The flowline was then leak tested and covered with concrete mud mats.

“Our Montrose team has considerable experience of this type of project in the North Sea, and so we were able to quickly respond to BP’s flowline installation request,” says Doug Davidson, managing director, Mooring Systems Ltd.

Projects

Riser Installation

Location: India Client: ONGC Mooring Systems installed a 400mt high pressure riser offshore India. Due to the nature of...

Westaf Stand Alone Mooring

Location: Nigeria Client: ABC Maritime Water Depth: 65m Tanker: 250,000 DWT Seastate: Hs = 5m

DIDON TCMS Installation

Location: Tunisia Client: PA Resources Water Depth: 80m No. of Risers: 1 + Umbilical Seastate: Hs = 7m

View all Projects →

Equipment Hire

Mooring Components

The mooring node is for connecting the three legs for the TCMS mooring, and the chafe chain on the upper lug of the node. Built by Vicinay in Spain, the node weights 12 tonne and fits 130mm Shackles .

76mm RQ4 Chain

Mooring systems Limited has presently 20,000 ft of 76mm anchor chain grade R4 new and unused in stock. Manufactured by Vicinay in Spain this chain is available for rental or purchase.

View all Equipment Hire →

Recent Projects

Masirah Oil

Client : Masirah Oil Location : Oman Services provided : Supply of 750mt of 6” Saturn Manuli hose , installation procedures , installation equipment , and installation team .

Sarost

Client: Sarost Location: Tunisia Services provided: Installation equipment, including 400te mobile carousel , tensioner , loading arm , and turntable . Full rigging team , and carousel technicians .

Kris Energy

Client : Kris Energy Services provided : Project engineering / client rep .